Mobilization of equipment

APPROACH:

We embraced the challenges and quickly developed a game plan. We made all the height and weight calculations, determined which hauling trailers would be required, obtained all the required Provincial approvals, made arrangements with a barge company and allocated the necessary resources to get the equipment to site in advance of the deadline.

OUTCOME:

All the equipment not only got to site when it was needed but also came in below budget. In fact, our hauling division was key to getting the job done as third party hauling companies would have made the operation cost prohibitive and we would not have been able to meet the tight timeline.